torsdag 15. oktober 2009

The snow has arrived

They say its early, and it is causing some complications regarding getting stuff to the site...imagine what its going to be like. All the columns are ready and the preparation for the concrete floor is about to finish, but are being delayed due to the late arrival of a tank.  Well, this is the first hurdle so far, and it is not a big one.                                                     
The entrance shaft to the technical room.


The outline of shower/toilet niches...looks so small in plan.
The photo below shows the three rows of concrete columns that will carry the load of the house, pluss 600 kg/m2 of possible snow. As you see they are slightly higher than the ring foundation, to elevate this part of the cabin. My worry is how the landscape facilitates this level difference now that we had to remove all the soil. My guy with the tractor says its going to be great, and by the look of all the gravel that he has put there it looks promising.

Ingen kommentarer:

Legg inn en kommentar